Method Statement from TimberSolve

Method Statement for the fixing of Flooring and the subsequent building-up of Party Walls for use with Cullen JH/JHI Masonry Hangers

We act as Consulting Engineers for Cullen Building Products and further to your request for information pertaining to the above, we comment below on the performance of Cullen JH/JHI masonry hangers where a partial cure exists in the supporting mortar beds, and no top courses are present above the hangers. The intention is to help in developing a method statement for the fixing of flooring and the subsequent building-up of party walls where Cullen masonry hangers are used. Before this is done, pertinent background data is reviewed below under the following headings: (i) hanger capacity at full cure with top courses, (ii) hanger capacity with no mortar/top courses, (iii) mortar bed capacity at full cure without top courses, (iv) mortar bed cure development, (v) site tests (vi) conclusions, (vii) recommendations.

(i) Cullen JH/JHI masonry hanger capacity at full cure with top load
Requirements for load testing and assessment of safe working loads of masonry hangers are given in BS6178: 1990 'Joist Hangers - Part 1. Specification for joist hangers into masonry walls of domestic dwellings'. This states that joist hangers should be tested at least 28 days after the test walls have been constructed, traditionally this having been done with a minimum of 3 masonry courses above the hanger. Cullen JH/JHI masonry hangers were tested and assessed to the requirements of this standard by both CERAM and Coventry University during the period May-October 2001. A total of 60 tests were conducted on hangers of various size, and blocks of various crushing strengths. These showed the dominant failure mode was crushing of the block beneath the hanger, with a characteristic hanger failure load (5% probability of failure) of 15kN. A corresponding safe working load of 7.54kN was recommended for all masonry crushing strengths greater than 2.8N/mm2 on all hanger widths. Because these BS6178 loads are inextricably linked to a 28 day cure period, and at least 3 courses of cured masonry being present above the hangers, they effectively relate to the hanger capacity in the finished structure, rather than being of any great relevance during the build process, where construction loads are applied with neither a full cure in the masonry or a top load being present.
(ii) Cullen JH/JHI masonry hanger capacity with no mortar/top load
To establish a hanger capacity more appropriate to the construction process, tests were later carried out at Cullen Building Products premises with JH/JHI masonry hangers sitting on loose 3.5N/mm2 blocks with no mortar present. These blocks were free to rotate; i.e. no other masonry tied in on either side, and no masonry above. The mean failure load established from 5 such tests, was 6.6kN (approx 45% of the BS6178 value), giving a corresponding safe working load of approx 3kN. The failure mode on this occasion was bending/straightening of the hanger top flange.

(iii) Mortar bed capacity at full cure without top courses present
Having established both lower and upper bound capacities for the hanger itself, attention then shifted to the mortar bed capacity immediately beneath the block upon which the hanger is placed. This is subject to compression from the joist reaction itself, and to bending since this load is applied near the edge of the block rather than on its centreline. When no top courses exist above the hanger, this bending component dictates the capacity of the bed joint. Our calculations indicate that a 600mm length of designation III mortar in flexure on 100mm blockwork will sustain a characteristic failure load (5% probability of failure) at full cure of 5kN - 6kN, applied to the inside face of the blockwork. This would equate to a safe working load of approx 1.6kN if a safety factor typical of that used in masonry design were to be applied. When top courses are later added, this mortar bed capacity will increase.
One assumption adopted in deriving this mortar bed capacity is that the hanger is fitted tightly to the blockwork. If a small gap exists between the hanger face and the wall, then the load eccentricity will increase and the capacity of the mortar bed will drop dramatically. To ensure the hanger is fitted tightly to the wall, it is therefore recommended that return style masonry hangers are used, i.e. Cullen JHR/JHIR masonry hangers.

(iv) Mortar bed cure development
Since the mortar bed capacities discussed above relate to full-cure, it is important to establish how quickly they develop. We have only been able to locate one reference (BRE Digest 360) giving indicative bond strength development values for various mortars with cure time. In the absence of more specific data, it is assumed that compression strength will follow a similar trend. The data relates to mortar curing in laboratory temperatures at 20°C. No data has been located for cure development at lower temperatures, although we do know it will be slower. The Digest suggests Designation III mortar will develop over 70% of its 28-day bond strength after 3 days at 20°C, with over 95% of its strength being attained after 7 days at 20°C.

(v) Site tests
In order to validate the above estimates of the strength of Cullen JHR/JHIR masonry hangers and of the mortar beds beneath during the build process, practical site tests to destruction were conducted in June and August 2002 on floor sections constructed on two sites managed by Bovis Homes Ltd. On both sites, the final two courses of masonry immediately below the hanger locations were built-up during the late afternoon of the day before the tests. On both occasions the weather conditions were dry and warm throughout. Load testing to failure was then carried out the day after, some 18-21hrs after the top courses had been laid.
On both sites a pair of joists were installed 600mm apart, simply supported on Cullen return style 75x225 deep JHR masonry hangers. Chipboard was laid on top of the joists adjacent to the load-bearing walls, and once props had been installed 50mm beneath the hangers to arrest any collapse, palletised packs of concrete blocks were then loaded onto the joists near to the wall junction via a telescopic loader until failure occurred. On each site, this operation was first conducted adjacent to the party wall bearing (constructed using 100mm high density concrete block), and then repeated at the opposite external wall bearing (constructed of 115mm lightweight concrete block) once the failed party wall bearing had been temporarily reinstated to its original level and supported on props from beneath. This procedure was then repeated on a second section of wall, using two new joists, yielding a total of 4 test results for each site (2 party wall junctions and 2 external wall junctions). By measuring the average weight of the concrete blocks used to load the joists, the spans of the joists involved, and the positions at which the load was applied in each case, the load applied to each hanger when failure occurred could be calculated. The results are summarised below :

Site Hanger failure load - party wall junction (100mm dense conc. block) Hanger failure load - external wall junction (115mm lightweight block) Failure mode
Test 1 Test 2 Test 1 Test 2
Lowestoft (June 2002) 4.7kN 5.2kN 3.8kN 3.8kN Unbending of the hanger top flange
Gosport (Aug 2002) 4.5kN 4.1kN 3.9kN 4.0kN Unbending of the hanger top flange

As can be seen, failure in all cases was by unbending of the hanger top flanges, at somewhat lower loads than had been determined previously in laboratory tests (see section ii). Contrary to the indications given by calculations (section iii) and the relatively early cure of the mortar (section iv), no failure of the mortar was observed. Tests on joists which were both tightly fitting between the walls, and with a gap of up to 10mm in the hanger, suggested this had no influence on the failure loads/modes observed.
In summary, the site testing carried out suggests that Cullen JHR/JHIR masonry hangers with no top courses present will fail by unbending/straightening of the metal top flanges at a load of approx 3.8kN on lightweight block, and slightly higher values on denser blocks. Provided the masonry courses beneath the hangers are cured for a period of at least 18hrs, this will be the maximum load the joist platform can support before additional masonry courses are added.

(vi) Conclusions
In summary, we believe loads of approximately 3.8kN (per joist) are required to unbend/straighten the top flange of Cullen JHR/JHIR hangers when no masonry courses exist above the hanger. Where sufficient top courses do exist above the hanger, and the masonry cure is fully developed, the load capacity of the hanger connection will ultimately be dictated by masonry crushing at a value of approx 15kN.

Two situations exist during construction for which the development of method statements would be desirable. The first relates to the time at which the floor decking might be fixed after the supporting walls have been built and the joist platform has been installed. The load which we estimate one carpenter (0.95kN) carrying one sheet of 22x600x2440mm chipboard (0.24kN) will impose when he stands directly on a joist near the hanger is 1.2kN. Site tests indicate that the corresponding safety factor against the top flange of the joist hanger unbending/straightening is approximately 3, and that provided dry/warm conditions prevailed during the initial mortar cure, this operation can be safely carried out the day after the masonry courses beneath the floor have been laid. To comply with the 1.2kN maximum load requirement on any joist, boards should be stacked with their 2.4m direction perpendicular to the joists (laid across the joists), with no more than 5No. 22x600x2440mm boards stacked on any one joist.

The second situation for which a method statement is desirable is the time at which the sheathed floor can then be used as a working platform from which to construct further masonry courses, and what the corresponding maximum applied construction loads can be. From site tests it is known that a maximum construction load of approx 1.3kN should be imposed on Cullen JHR/JHIR masonry hangers, if a factor of safety of approximately 3 is to be maintained against the hanger top flange unbending/straightening. Assuming one operative carrying and laying blocks will impose no more than 0.95kN per joist, this suggests the loading out of blocks ready for installation must impose no more than 35kg/joist (60kg/m run of wall). This indicates that only a single course of high density (1500kg/m3) concrete blocks can safely be loaded on the floor in a single line across the joists before being built into the wall. In this case the safety factor against the hanger top flanges unbending/straightening will again be approximately 3. To assure the necessary confidence in the degree of cure that exists in the masonry at the time, it is recommended that this operation should only be carried out when the masonry beneath the floor has cured for a minimum of 3 days. Should it be necessary to load any more than one course of blockwork in a single line across the floor at any one time, or wall construction is necessary before 3 days, then it is recommended that independent support is provided to the floor, or an alternative working platform is constructed.

(vii) Recommendations
From the analysis and testing described above the following recommendations can be given :

Fixing of Flooring
Site tests have indicated that fixing of flooring can safely be carried out on floors supported using Cullen JHR/JHIR masonry hangers the day after the masonry has been laid, provided dry/warm conditions have prevailed. Should the temperature drop below 15°C for any significant length of time during this initial cure period, or installation on the same day is desired, then independent support should be provided to all joists by means of temporary props designed to carry the requisite loads. Boards should be stacked no more than 5 high, with their 2.4m direction perpendicular to the joists (laid across the joists), and no more than one stack being placed on any one joist.

Building-up of party walls
Site tests indicate that construction loads no greater than 1.3kN should be applied to Cullen JHR/JHIR masonry hangers if a factor of safety of 3 is to be maintained against the hanger top flange unbending/straightening. In addition to the loads imposed by a site operative laying masonry courses, this is sufficient to enable one course of high density concrete blockwork to be loaded on the floor at any one time, in a single line across the joists, before they are installed above the hangers. This operation should only be carried out when the masonry beneath the floor has cured for a minimum of 3 days. Additional masonry courses can then be loaded-out in a similar manner and constructed in single courses. Should it be necessary to load any more than one course of blockwork in a single line across the floor at any one time, or party wall construction needs to proceed before 3 days have elapsed, then it is recommended that suitably designed independent support is provided to the floor, or an alternative working platform is constructed.

In both situations given above, it is essential that return-style Cullen 'JHR' or 'JHIR' masonry hangers are used throughout. These will ensure the hangers are seated flush with the inside face of the blockwork, and that the safety factor against hanger failure is the maximum attainable. Joists must be seated firmly against the back of the hanger, and under no circumstances should this gap exceed 6mm. The above statements have specifically been developed for use with Cullen JHR/JHIR masonry hangers, and are only valid where these hangers are used. No responsibility is accepted for the use of this information for any other type of masonry hanger.

We trust the above is of some assistance to you.

Yours faithfully,
For TimberSolve Ltd

Dr L.R.J Whale
Director